Liquid Oxygen Tanks Installed at the Benghazi Steel Complex

Heavy machinery hands over the baton: Major structural work draws to a close as teams pivot to interior finishing and utility installation across the site.

Another major item of equipment for the Benghazi Iron and Steel Complex has now been presented to the Air Separation Unit (ASU) in the form of its liquid oxygen tanks. 

Heavy-duty cranes lifted the tanks into place and mechanically installed them at the unit. In time, they will hold the oxygen needed for the CDRI plant and they will help to keep a steady supply when production begins. Oxygen storage is a bit more complicated than it sounds. It will be kept in liquid form inside these tanks at around -183°C. Liquid oxygen can be re-gasified when required by the plant and pumped through the pipeline network to where it is needed . 

The tanks also give the plant some breathing room on supply. When demand is low, oxygen can be stored and used when demand is high. The reserve can also be used to hold oxygen if the main Air Separation Unit is taken off-line for scheduled maintenance or an unscheduled shutdown. 

The piping will be connected, measuring instruments and safety valves will be installed and the tanks will be hydrostatically and pneumatically tested. Having done that work, the team can begin preparing for trial operation. 

Much of the work at the steel complex is visible as buildings and steel structures rise across the site. It’s a different kind of progress. Installation of equipment such as these tanks has to do with preparing the systems that will keep the plant going on a day-to-day basis. 

For now the tanks are there and work continues around them. Next up is getting the connections, instruments and testing done so the system is ready for the next stage. 

References: 

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

LCC Teams Step In After Fire At Al-Qawarsha Substation

Insights|2026-09-11

LCC Teams Step In After Fire At Al-Qawarsha Substation

LCC emergency teams quickly stepped in to tackle a fire at Al-Qawarsha substation in Benghazi, providing critical firefighting and medical support.

Read more →

Massive Tanks Rise Over Tosyali SULB as Installation Begins

Insights|2026-09-09

Massive Tanks Rise Over Tosyali SULB as Installation Begins

Heavy equipment installation begins at Tosyalı SULB with new gas tanks for the Air Separation Unit

Read more →

Installation Advances at Tosyali SULB Plant

Insights|2026-09-04

Equipment and Steel Installation Progress at Tosyali SULB

Work at the Tosyali-SULB complex in Benghazi advances above ground with steel framework erection, concrete casting, and mechanical equipment installation.

Read more →

Zulfa Begins Key Facility Finishings

Insights|2026-09-03

Zulfa Begins Key Facility Finishings

Zulfa Food Industries moves into its finishing phase, progressing on interior fit-outs, wiring, and site landscaping across key facilities.

Read more →

Insights

Hawari Begins Technical Testing for Line 2 Start-Up

Hawari's second production line enters technical testing, focusing on system tuning and equipment integration prior to full operational launch.

Read more →

Insights

Hawari Cement Plant Reactivates Second Production Line

Hawari Cement Plant reactivates its second line after 13+ years, boosting local supply for Libya’s reconstruction through safe, in-house rehabilitation.

Read more →