Development Work at the Tosyali SULB Industrial Project

The Tosyali SULB steel complex in Benghazi is progressing steadily with the completion of one of the first and most important phases of the project. This week teams from the site confirmed that all piling work is complete which allowed them to focus on the next stages of development across a number of areas of the site.

With foundations complete, work has moved more towards concrete works, structural steel installation and continuing development of key operational buildings. Work in the Heat Recovery Area has recently finished. Foundation and beam concrete works have also been completed in the ASU Compressor room. Meanwhile, teams continue their reinforcement and formwork activities at the Pipe Rack, Raw Water Area, CDRI Passivation Silos, Main Compressor Building and Dust Collector F73.

The project is also becoming more visible above ground as steel columns and beams are being installed throughout the Reduction Area and the Storage Facilities. The reports also show how much work is being done each day. On site, there are more than 260 engineers, technicians, contractors and support staff, and they are supported by a large fleet of heavy construction equipment. Multiple sections of the project are being worked on simultaneously.

Work on the Benghazi steel complex will continue and it will be one of the most important industrial projects in Libya. Completion of each phase brings the country one step closer to a project expected to boost the country’s industrial sector and open the door to future economic growth and job creation.

References:

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyali Sulb Steel Industries Joint Company.” Tosyali Holding,

www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

LCC Teams Step In After Fire At Al-Qawarsha Substation

Insights|2026-09-11

LCC Teams Step In After Fire At Al-Qawarsha Substation

LCC emergency teams quickly stepped in to tackle a fire at Al-Qawarsha substation in Benghazi, providing critical firefighting and medical support.

Read more →

Massive Tanks Rise Over Tosyali SULB as Installation Begins

Insights|2026-09-09

Massive Tanks Rise Over Tosyali SULB as Installation Begins

Heavy equipment installation begins at Tosyalı SULB with new gas tanks for the Air Separation Unit

Read more →

Installation Advances at Tosyali SULB Plant

Insights|2026-09-04

Equipment and Steel Installation Progress at Tosyali SULB

Work at the Tosyali-SULB complex in Benghazi advances above ground with steel framework erection, concrete casting, and mechanical equipment installation.

Read more →

Zulfa Begins Key Facility Finishings

Insights|2026-09-03

Zulfa Begins Key Facility Finishings

Zulfa Food Industries moves into its finishing phase, progressing on interior fit-outs, wiring, and site landscaping across key facilities.

Read more →

Insights

The Story Behind Alushibe News

Discover Alushibe News, the official platform sharing project updates, company milestones and the people shaping Alushibe Holding Group’s growth.

Read more →

Insights

New Infrastructure At Zulfa Food Industries

Zulfa Food Industries advances factory infrastructure with new security systems, electrical installations and transformers to support future production.

Read more →