New Equipment Arrives. Construction Progress at Benghazi Steel Project

Latest development of Tosyali-SULB

Construction continues to move forward at the Tosyali-SULB Direct Reduced Iron (DRI)complex in Benghazi. One of the latest developments was the arrival of the Top Gas Scrubber, which is a key piece of equipment that will be installed as part of the plant's reduction furnace. Once the process of installation is completed, it will cool and clean process gases, helping improve the efficiency of the DRI production process. Because of its size, the unit was transported to the site under a coordinated operation involving traffic police and emergency services.

‎

Construction teams are also continuing to work on the 220 kV substation, where concrete is being poured for the foundations that will support the site's future power infrastructure. Not only new technical equipment was delivered, but also oxygen tanks have arrived and work on the utility systems is continued.

‎

Elsewhere on site, structural steel installation is progressing in the Reduction Area, Reformer Area and Gas Compressor Building. While piling and concrete works are continuing in the Cooling Tower area, and masonry work is underway on the services building.

‎

The latest update shows steady progress across the project, concrete works had reached 64 percent completion, backfilling stood at 63 percent and structural steel installation had reached 20 percent, with work continuing across multiple sections of the future steel complex.

‎

References:

1.“Tosyali Sulb Steel Industries Joint Company. ” Tosyali Holding,

www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

The Scale Of Tosyali-SULB Is Becoming Impossible To MissThe Scale Of Tosyali-SULB Is Becoming Impossible To Miss

Insights|

The Scale Of Tosyali-SULB Is Becoming Impossible To Miss

Construction at the Tosyalı-SULB Benghazi steel complex moves above ground with completed piling, rising steel frames, and key equipment installation.

Read more →

Hard Hats Off, Football Boots On at LCCHard Hats Off, Football Boots On at LCC

Insights|

Hard Hats Off, Football Boots On at LCC

Libyan Cement Company (LCC) launches its 2nd employee football league to boost fitness, teamwork, and employee connection.

Read more →

Benghazi’s Steel Future Is Becoming Hard To MissBenghazi’s Steel Future Is Becoming Hard To Miss

Insights|

Benghazi’s Steel Future Is Becoming Hard To Miss

Benghazi’s Tosyalı-SULB site transforms from ground prep into a connected industrial steel complex with key machinery arriving.

Read more →

Strong Skills And Safer Plants As LCC Invests In Its PeopleStronger Skills And Safer Plants As LCC Invests In Its People

Insights|

Strong Skills And Safer Plants As LCC Invests In Its People

LCC invests in workforce development with practical firefighting safety and specialized machinery vibration analysis training across its plants.

Read more →

PREVIOUS
Electrical Infrastructure Advancements at Zulfa Production

Insights

Electrical Infrastructure Advancements at Zulfa Production

Discover the latest updates on electrical infrastructure at the Zulfa production facility in Benghazi as power systems and generator installations advance.

Read more →

NEXT
The Story of Libyan Cement Company (LCC)

Insights

The Story of Libyan Cement Company (LCC)

Discover the 60-year journey of Libyan Cement Company (LCC), its role in building Libya, and its new future as part of Alushibe Holding Group.

Read more →