From Steel Installation to Power Connection. A Busy New Stage at Tosyali-SULB

From Steel Installation to Power Connection. A Busy New Stage at Tosyali-SULB

Piling work is now complete and work now moves higher above ground. Steel columns and beams are going up across the site, foundations are being poured for some of the plant’s major facilities, and the first pieces of mechanical equipment are starting to be installed. 

‎

The activity is dispersed over very different parts of the future complex. Teams are working around the CDRI Passivation Silos, the seawater desalination buildings, the gas compression units and the 220 kV Substation. More steel structure is being assembled in the Reduction Area and along the Pipe Rack. The travelling wheels for the stacking equipment in the oxide storage area have also begun to be worked on. 

‎

The new 220 kV transmission line will connect Tosyali SULB to the Kogelex Power Generation Station north of Benghazi. When it’s up and running, the complex will churn out between 68 and 80 megawatts of electricity. 

‎

Much of the work to make that connection has been done already. Steel transmission towers are assembled, civil works are complete and as required, materials have been delivered. The teams have also completed the underground section of the project, which is the 650-metre cable route connecting the overhead towers to the main feeder at Kogelex. 

‎

There are currently close to a thousand engineers, technicians and workers working on the site, with several teams working in different parts of the complex at the same time. 

‎

Much of the work a few months ago was below the surface, focused on foundations. Now steel structures are going up all over the site, equipment is beginning to appear, and the power connection that will ultimately feed the plant is taking shape alongside it. 

‎

References: 

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Work Advances at Raw Water BasinWork Advances at Raw Water Basin

Insights|

Work Advances at Raw Water Basin

Round-the-clock concrete work advances at the Benghazi steel complex Raw Water Basin.

Read more →

Benghazi Steel Project Receives New EquipmentLatest development of Tosyali-SULB

Insights|

Benghazi Steel Project Receives New Equipment

Discover the latest construction updates at the Tosyali-SULB DRI steel project in Benghazi, including key equipment arrivals and structural progress.

Read more →

The Next Chapter in Benghazi's Largest Industrial ProjectDevelopment Work at the Tosyali SULB Industrial Project

Insights|

The Next Chapter in Benghazi's Largest Industrial Project

Tosyali SULB Benghazi completes key foundation phases and advances structural steel installation for Libya’s largest industrial steel complex.

Read more →

The Story of Libyan Cement Company (LCC)Libya cement company office

Insights|

The Story of Libyan Cement Company (LCC)

Discover the 60-year journey of Libyan Cement Company (LCC), its role in building Libya, and its new future as part of Alushibe Holding Group.

Read more →

PREVIOUS
From International Headlines to the Construction Site

Insights

From International Headlines to the Construction Site

Tosyalı SULB in Benghazi featured in Newsweek as construction advances, building key steel structures and grid links for European markets.

Read more →

NEXT
Tosyali SULB: $2.5B from Benghazi to Global Markets

Insights

Tosyali SULB: $2.5B from Benghazi to Global Markets

Construction advances at Tosyali SULB's $2.5B steel complex in Benghazi, a major step toward green steel production for domestic and export markets.

Read more →