The teams are now working on concrete and structural work on the Raw Water Basin at the Tosyali-SULB steel complex in Benghazi, where work continues around the clock. 

‎

Crews worked through the day and night to keep this part of the project on track. So far, 1,622 cubic meters of concrete have been poured out of the planned 2,377 cubic meters. 

‎

The engineering and technical teams on site are watching the work itself closely. Pouring concrete takes time and coordination, particularly when work continues across shifts so teams are overseeing each stage while also watching for safety and quality of work being done. 

‎

In time the Raw Water Basin will be incorporated into the overall utility system for the steel complex. Once its concrete structures are completed, work can proceed in the surrounding utility areas and help prepare this part of the plant for testing and technical commissioning later. 

‎

The priority is to complete the remaining concrete work. This is one part of a much larger project but, like many of the areas now taking shape across the site, other work relies on it being prepared. 

‎

The Raw Water Basin is nearing completion and with teams still working into the evening the next stages of work around it can commence. 

‎

References: 

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Tosyali SULB: $2.5B from Benghazi to Global MarketsFrom Benghazi to Global Markets. Inside the $2.5 Billion Tosyali SULB Project

Insights|

Tosyali SULB: $2.5B from Benghazi to Global Markets

Construction advances at Tosyali SULB's $2.5B steel complex in Benghazi, a major step toward green steel production for domestic and export markets.

Read more →

From International Headlines to the Construction SiteFrom International Headlines to the Construction Site

Insights|

From International Headlines to the Construction Site

Tosyalı SULB in Benghazi featured in Newsweek as construction advances, building key steel structures and grid links for European markets.

Read more →

New Infrastructure At Zulfa Food IndustriesNew electrical infrastructure and transformers at Zulfa Food Industries factory

Insights|

New Infrastructure At Zulfa Food Industries

Zulfa Food Industries advances factory infrastructure with new security systems, electrical installations and transformers to support future production.

Read more →

Safety Begins with the People on SiteSafety Begins with the People on Site

Insights|

Safety Begins with the People on Site

The Safety and Industrial Security Department launches a practical safety training program in August, empowering employees to identify risks early and maintain

Read more →

PREVIOUS
LCC Safety Training and Green Care

Insights

LCC Safety Training and Green Care

Libyan Cement Company advances workplace safety with hands-on firefighting training and maintains green areas to improve air quality around its facilities.

Read more →

NEXT
Beyond Oil. A Different Picture Of Libya’s Economic Future

Insights

Beyond Oil. A Different Picture Of Libya’s Economic Future

Fawasel Media has published a recent article that focuses on Libya’s investment potential and the industries that could flourish alongside the energy sector.

Read more →