Skip to main content

Work Continues Across the TosyaliSulb Steel Complex

Pillar Installation at Tusyali sulb project

Work has continued at the Tosyali-SULB steel complex in Benghazi, with construction teams working across several areas of the site as the project moves into its next stage. One of the updates from the site has been the piling works, which are now more than 95% complete. With only 74 piles left to finish, one of the project's biggest early construction stages is now close to completion.


Work has also continued across many other complex's facilities such as CDRI Warehouse and also carried out additional concrete works in the Cooling Tower area and the Main Control Building. Recently the most focus was on the Oxide Screen Station, the Dust Collector F83 system and the Reformer Area, where steel installation and other structural work continue to take shape.


As construction continues, the numbers show steady progress across the project. Concrete works are now at 63% completion, while piling, steel installation and backfilling continue to move forward alongside one another.


More than 260 engineers, technicians, contractors and workers are on site each day, contributing to the project as new materials arrive and different parts of the complex continue to develop.


While changes happen they become easier to see with every update. More buildings are taking shape, more structures are being completed and another important phase of the project is steadily coming together. Every stage completed is the result of the work taking place on site each day, bringing the TosyaliSulb steel complex one step closer to becoming a reality.


References:

1.“Tosyali Sulb Steel Industries Joint Company.

” Tosyali Holding,www.tosyaliholding.com.tr/en/our-scope-of-activity/group companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Beyond Oil. A Different Picture Of Libya’s Economic FutureAhmed Gadalla - Slub Project

Insights|

Beyond Oil. A Different Picture Of Libya’s Economic Future

Fawasel Media has published a recent article that focuses on Libya’s investment potential and the industries that could flourish alongside the energy sector.

Read more →

Work progress at the Benghazi Steel ComplexWork progress at the Benghazi Steel Complex

Insights|

Work progress at the Benghazi Steel Complex

Construction at the Tosyali-SULB steel complex in Benghazi is advancing rapidly, with foundation work nearing completion and key equipment delivered.

Read more →

Looking After the People Behind the WorkAerial view of an industrial construction site near the sea with concrete structures, a concrete pump truck, a mixer, and earthmoving equipment.

Insights|

Looking After the People Behind the Work

Libyan Cement Company advances workplace safety and employee well-being by relocating contractor housing and settling medical insurance obligations.

Read more →

PREVIOUS
Work progress at the Benghazi Steel Complex

Insights

Work progress at the Benghazi Steel Complex

Construction at the Tosyali-SULB steel complex in Benghazi is advancing rapidly, with foundation work nearing completion and key equipment delivered.

Read more →

NEXT
Electrical Infrastructure Advancements at Zulfa Production

Insights

Electrical Infrastructure Advancements at Zulfa Production

Discover the latest updates on electrical infrastructure at the Zulfa production facility in Benghazi as power systems and generator installations advance.

Read more →