A Fresh Look at What’s Happening Inside Zulfa

Zulfa has seen plenty of activity, with work continuing on the factory as well as the hotel. Construction crews have been busy finishing buildings, prepping storage space and installing new equipment. Some areas of the project are still under construction, and some areas are starting to enter the final phases of interior work.
Among the latest arrivals was a shipment of six stainless-steel water tanks that will store treated water for the factory. The tanks combined can hold up to 255,000 litres and are made from a type of stainless steel that is suitable for food production. When the factory is up and running it will need a steady flow of treated water to maintain hygiene standards especially when it involves making beverages.
Meanwhile work goes on inside the factory buildings and also the preparation of new machinery for future use. The raw-material warehouses have already been plastered, sanded and cleaned. Workers are now preparing the floors and the surrounding ground for the next stage of construction. Preparation of the storage areas is an important part of getting the factory ready because in the end the storage areas will be needed to store the materials required for production.
The admin buildings are starting to take shape as well. Workers have been installing tiles, finishing off walls and installing an electric lift in the main administration building. Work is ongoing on the interior of the technical administration building, as well as preparations for the electricity and air conditioning systems. Work is also under way on a footbridge linking parts of the site.
Meanwhile, the main factory building is nearly complete with its basic systems. Teams are working on the sewer network and planning the electrical connections, while concrete and insulation work is being done in the weekly-supply storage areas.
Work also has been progressing at the hotel where the focus now is mainly on completing the interiors and getting the facilities ready for future guests. In the café, workers are laying porcelain tiles and adding wood-effect finishes, while in other areas electrical connections, partitions and interior fittings are being prepared.
The hotel kitchen is being fitted out with new equipment and installation has already begun. Workers are completing underground service connections, preparing the roads and walkways outside the buildings and prepping the landscaped areas for planting. Work is also underway on the sports court, adding another feature to the hotel facilities.
The project team has been meeting regularly to monitor progress and address issues as they arise, as there are many different activities going on. Construction, electrical, equipment deliveries and interior finishing all have to be coordinated, especially when multiple teams are working in the same areas.
A lot of the recent work has been about getting the details right, looking at the project in the round. At the factory, the work is focused on preparing the storage areas and
completing the buildings and putting the necessary systems in place. There’s more attention being paid to the hotel’s interiors, equipment and outdoor spaces that will be used by guests.
There is still work to be done before either facility is ready to open, but the latest developments show how the project is slowly coming together. As equipment arrives and construction continues at the site, Zulfa is approaching the time when the new facilities can start operating.
References:
1.Zulfa Food Industries — https://www.zulfa.ly/
2.Ahmed Gadalla, Building the Future of Libya. (2026). Ahmed Gadalla | Alushibe – Building Libya’s Future. https://www.ahmedgadalla.com/
More Insights

Insights|
من تركيب الهياكل الفولاذية إلى الربط الكهرباني.. مرحلة جديدة حافلة بالأعمال في توسيالي صلب

Insights|
Zulfa Site Development & Construction Update

Insights|
Primary Piling Work At Benghazi Steel Complex Completed

Insights|
New Infrastructure At Zulfa Food Industries
Insights
Benghazi’s Steel Ambitions Are Becoming Reality
Insights