Fresh Finishes and Busy Floors Across Zulfa

There’s still work going on at Zulfa’s factory and hotel projects in Benghazi and there have been quite a few changes recently on both sites. Workers are busy at the factory with preparation of production areas, installation of wall panels and finishing parts of administrative buildings.
The plant’s areas for production and storage are still being prepared. Reinforcement steel has been going in and the floors have been preparing for concrete. There is also plumbing work being done and sandwich panel installation being done by a Turkish contractor and in the storage and maintenance areas, work is also progressing, with the teams levelling floors, clearing up construction debris and putting insulation on the walls.
The office buildings of the plant are also progressing. Work continues on the lift, painting and interior finishes in the main building while windows are being installed. The technical administration building is a little further along in some areas with floor tiling in progress and the walkways outside nearly finished. Workers are also putting in air-conditioning and hooking up electrical connections.
Electricity is another area the team has been working on for the project. The contractors are preparing the cable routes and connections in the electrical room to be later connected to the factory’s power system. It’s one of those jobs that you don’t see from the outside, but it’s got to be done before the plant can run.
Additionally, Zulfa’s Security Department ran a basic computer skills course for younger employees. The idea was to help them gain confidence with computers and learn skills that could be applied in their daily work.
The changes are becoming more apparent at the hotel. Now the café has flooring, interior decoration and restrooms. Workers are still installing CCTV cameras and adding wood-effect finishes, but most of the main interior work is already complete. While painting and decoration of the dining room is now complete and the team are checking the final details before moving on to the next stage.
Outside, the workers are preparing the roads for asphalt and finishing the walkways that will connect different parts of the hotel. The fencing surrounding the sports court is also almost complete. Another job done recently is the installation of the central water heaters in the hotel. They still need to be tied into the water distribution system and tested before they can be used.
What's interesting is that these two projects look so different right now. Still at the factory there are floors to finish, walls to prepare and connections to be made. At the hotel you can already start imagining what some of the spaces will be like when everything is finished. It’s a good reminder that you can be working on the same project, that different parts of a building can be at completely different stages, and that there is usually a lot more going on than you can see from the outside.
References:
1.Zulfa Food Industries — https://www.zulfa.ly/
2.Ahmed Gadalla, Building the Future of Libya. (2026). Ahmed Gadalla | Alushibe – Building Libya’s Future. https://www.ahmedgadalla.com/
More Insights

Insights|
Primary Piling Work At Benghazi Steel Complex Completed

Insights|
خبرات عالمية تلتقي بالكفاءات المحلية لتحديث مصانع شركة الأسمنت الليبية

Insights|
صافرة تنطلق في أسبوع حافل بالشركة الليبية للأسمنت

Insights|
Benghazi Steel Project Receives New Equipment
Insights
A Fresh Look at What’s Happening Inside Zulfa
Insights