Construction Progress Continues At The Benghazi Steel Complex

Aerial view of concrete column foundations, rebar, piling rigs and trucks at the Benghazi steel complex construction site

Construction actively remains busy at the Tosyali SULB steel complex in Benghazi, The latest updates are showing steady progress, the groundwork has been coming to an end and more visible stages of development have appeared. According to the latest report, engineers, contractors and other staff were active across the whole building site throughout the day.

‎

One of the clearest signs of that progress can be seen in the project's foundation works. Such as the deep piling operations that are now coming to an end, with most of the planned piles already installed across the site. The teams also have completed the casting of eight additional piles in the Cooling Tower area, bringing the project closer to finishing one of the most important early construction phases.

‎

Work also continues on the structure that will support the operation of the complex foundations for CDRI Passivation Silos are complete, while concrete work is ongoing at the 220kV, Main Control Room, Oxygen Reduction Building, Gas Treatment Area and Duct Bridge.

‎

The steel installation is also moving forward, more than 4,900 tonnes of structural steel have been installed so far, including 126 tonnes added during the work period. Engineers are also working on Reformer Area, Utility Compressor Room and warehouse facilities.

‎

The figures show continued progress across the whole project, heavy concrete pouring has reached nearly 60 percent completion, while earthworks and backfilling activities have passed the halfway mark. Every day, teams continue working on foundations, steel structures, utility systems and support facilities to ensure the project takes its final form in the near future.

‎

References:

1."Tosyalı Sulb Steel Industries Joint Company." Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Liquid Oxygen Tanks Installed at the Benghazi Steel ComplexIndustrial Substation Construction

Insights|

Liquid Oxygen Tanks Installed at the Benghazi Steel Complex

New liquid oxygen tanks have been installed at the Benghazi Steel Complex to secure steady supply and operational flexibility for the CDRI plant.

Read more →

Zulfa Moves Closer to Becoming an Operational FacilityHeavy machinery hands over the baton: Major structural work draws to a close as teams pivot to interior finishing and utility installation across the site.

Insights|

Zulfa Moves Closer to Becoming an Operational Facility

Zulfa Food Industries enters the final stages of construction. Read how interior finishing, utility setups, and facilities bring the project closer to launch.

Read more →

Benghazi Steel Project Receives New EquipmentLatest development of Tosyali-SULB

Insights|

Benghazi Steel Project Receives New Equipment

Discover the latest construction updates at the Tosyali-SULB DRI steel project in Benghazi, including key equipment arrivals and structural progress.

Read more →

Safety Begins with the People on SiteSafety Begins with the People on Site

Insights|

Safety Begins with the People on Site

The Safety and Industrial Security Department launches a practical safety training program in August, empowering employees to identify risks early and maintain

Read more →

PREVIOUS
NEXT