Equipment and Steel Installation Progress at Tosyali SULB

Installation Advances at Tosyali SULB Plant

More of the project is starting to rise above ground and work at the Tosyali-SULB iron and steel complex in Benghazi is beginning to change gradually. With the main piling work out of the way, attention is shifting to concrete, structural steel and the various facilities that will eventually comprise the plant. 

‎

Many parts of the complex are being worked on simultaneously. Reinforcement and concrete casting work is taking place around the CDRI Passivation Silos, water desalination facilities and NGPT Area. Work is also continuing on the Main Control Room, the main electrical substation and other transformer substations around the site. The columns and beams are going in and the Reduction Area, the Pipe Rack Area and the CDRI Warehouse are starting to take shape, giving these parts of the complex a much more defined shape than they had in the earlier stages of construction. 

‎

Some areas are getting into mechanical installation as well. In the Air Separation Unit, installation of an oxygen tank is in progress, and the work of the Bucket Wheel Stacker and Reclaimer in the Oxide Storage Area is in progress. 

‎

What’s happening across the site now is a combination of various stages. In some places, concrete work is still going on. In others, steel structures are going up. In places where the buildings are more advanced, equipment is starting to arrive and be put in place. 

‎

This allows us to follow the progress from one part of the complex to another. The project is no longer just about what is happening below ground. More of the buildings, structures and equipment that will make up the steel complex are beginning to take their place across the site. 

‎

References: 

1.Alushibe News. “Alushibe News.” Alushibe News, www.alushibenews.com

2.“Tosyalı Sulb Steel Industries Joint Company.” Tosyalı Holding, www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

From Steel Installation to Power ConnectionFrom Steel Installation to Power Connection. A Busy New Stage at Tosyali-SULB

Insights|

From Steel Installation to Power Connection

Tosyalı-SULB transitions to steel structure installation and 220 kV power line assembly, with nearly 1,000 workers on site.

Read more →

Zulfa Begins to Resemble Its Intended Facility DesignZulfa Begins to Look Like the Facility It Was Designed to Become

Insights|

Zulfa Begins to Resemble Its Intended Facility Design

Finishing work progresses across the Zulfa Food Industries site as buildings, interiors, infrastructure, and landscaping reach their final construction stages.

Read more →

Hard Hats Off, Football Boots On at LCCHard Hats Off, Football Boots On at LCC

Insights|

Hard Hats Off, Football Boots On at LCC

Libyan Cement Company (LCC) launches its 2nd employee football league to boost fitness, teamwork, and employee connection.

Read more →

New Infrastructure At Zulfa Food IndustriesNew electrical infrastructure and transformers at Zulfa Food Industries factory

Insights|

New Infrastructure At Zulfa Food Industries

Zulfa Food Industries advances factory infrastructure with new security systems, electrical installations and transformers to support future production.

Read more →

PREVIOUS
Zulfa Begins Key Facility Finishings

Insights

Zulfa Begins Key Facility Finishings

Zulfa Food Industries moves into its finishing phase, progressing on interior fit-outs, wiring, and site landscaping across key facilities.

Read more →

NEXT