New Equipment Arrives. Construction Progress at Benghazi Steel Project

Latest development of Tosyali-SULB

Construction continues to move forward at the Tosyali-SULB Direct Reduced Iron (DRI)complex in Benghazi. One of the latest developments was the arrival of the Top Gas Scrubber, which is a key piece of equipment that will be installed as part of the plant's reduction furnace. Once the process of installation is completed, it will cool and clean process gases, helping improve the efficiency of the DRI production process. Because of its size, the unit was transported to the site under a coordinated operation involving traffic police and emergency services.

Construction teams are also continuing to work on the 220 kV substation, where concrete is being poured for the foundations that will support the site's future power infrastructure. Not only new technical equipment was delivered, but also oxygen tanks have arrived and work on the utility systems is continued.

Elsewhere on site, structural steel installation is progressing in the Reduction Area, Reformer Area and Gas Compressor Building. While piling and concrete works are continuing in the Cooling Tower area, and masonry work is underway on the services building.

The latest update shows steady progress across the project, concrete works had reached 64 percent completion, backfilling stood at 63 percent and structural steel installation had reached 20 percent, with work continuing across multiple sections of the future steel complex.

References:

1.“Tosyali Sulb Steel Industries Joint Company. ” Tosyali Holding,

www.tosyaliholding.com.tr/en/our-scope-of-activity/group-companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

LCC Teams Step In After Fire At Al-Qawarsha Substation

Insights|2026-09-11

LCC Teams Step In After Fire At Al-Qawarsha Substation

LCC emergency teams quickly stepped in to tackle a fire at Al-Qawarsha substation in Benghazi, providing critical firefighting and medical support.

Read more →

Massive Tanks Rise Over Tosyali SULB as Installation Begins

Insights|2026-09-09

Massive Tanks Rise Over Tosyali SULB as Installation Begins

Heavy equipment installation begins at Tosyalı SULB with new gas tanks for the Air Separation Unit

Read more →

Installation Advances at Tosyali SULB Plant

Insights|2026-09-04

Equipment and Steel Installation Progress at Tosyali SULB

Work at the Tosyali-SULB complex in Benghazi advances above ground with steel framework erection, concrete casting, and mechanical equipment installation.

Read more →

Insights

Electrical Infrastructure Advancements at Zulfa Production

Discover the latest updates on electrical infrastructure at the Zulfa production facility in Benghazi as power systems and generator installations advance.

Read more →

Insights

The Story of Libyan Cement Company (LCC)

Discover the 60-year journey of Libyan Cement Company (LCC), its role in building Libya, and its new future as part of Alushibe Holding Group.

Read more →