Work Continues Across the TosyaliSulb Steel Complex

Pillar Installation at Tusyali sulb project

Work has continued at the Tosyali-SULB steel complex in Benghazi, with construction teams working across several areas of the site as the project moves into its next stage. One of the updates from the site has been the piling works, which are now more than 95% complete. With only 74 piles left to finish, one of the project's biggest early construction stages is now close to completion.


Work has also continued across many other complex's facilities such as CDRI Warehouse and also carried out additional concrete works in the Cooling Tower area and the Main Control Building. Recently the most focus was on the Oxide Screen Station, the Dust Collector F83 system and the Reformer Area, where steel installation and other structural work continue to take shape.


As construction continues, the numbers show steady progress across the project. Concrete works are now at 63% completion, while piling, steel installation and backfilling continue to move forward alongside one another.


More than 260 engineers, technicians, contractors and workers are on site each day, contributing to the project as new materials arrive and different parts of the complex continue to develop.


While changes happen they become easier to see with every update. More buildings are taking shape, more structures are being completed and another important phase of the project is steadily coming together. Every stage completed is the result of the work taking place on site each day, bringing the TosyaliSulb steel complex one step closer to becoming a reality.


References:

1.“Tosyali Sulb Steel Industries Joint Company.

” Tosyali Holding,www.tosyaliholding.com.tr/en/our-scope-of-activity/group companies/international-subsidiaries/tosyali-sulb-steel-industries-joint-company

More Insights

Heavy machinery hands over the baton: Major structural work draws to a close as teams pivot to interior finishing and utility installation across the site.

Insights|2026-08-13

Zulfa Moves Closer to Becoming an Operational Facility

Zulfa Food Industries enters the final stages of construction. Read how interior finishing, utility setups, and facilities bring the project closer to launch.

Read more →

Safety Begins with the People on Site

Insights|2026-08-28

Safety Begins with the People on Site

The Safety and Industrial Security Department launches a practical safety training program in August, empowering employees to identify risks early and maintain

Read more →

Ahmed Gadalla

Insights|2026-06-13

A Step Forward Telling The Full Story

Alushibe News examines claims about Ahmed Gadalla fairly and factually, including what the Fawasel investigation found regarding The Sentry's report.

Read more →

Insights

Work progress at the Benghazi Steel Complex

Construction at the Tosyali-SULB steel complex in Benghazi is advancing rapidly, with foundation work nearing completion and key equipment delivered.

Read more →

Insights

Electrical Infrastructure Advancements at Zulfa Production

Discover the latest updates on electrical infrastructure at the Zulfa production facility in Benghazi as power systems and generator installations advance.

Read more →