Work Continues Across the TosyaliSulb Steel Complex

Work has continued at the Tosyali-SULB steel complex in Benghazi, with construction teams working across several areas of the site as the project moves into its next stage. One of the updates from the site has been the piling works, which are now more than 95% complete. With only 74 piles left to finish, one of the project's biggest early construction stages is now close to completion.
Work has also continued across many other complex's facilities such as CDRI Warehouse and also carried out additional concrete works in the Cooling Tower area and the Main Control Building. Recently the most focus was on the Oxide Screen Station, the Dust Collector F83 system and the Reformer Area, where steel installation and other structural work continue to take shape.
As construction continues, the numbers show steady progress across the project. Concrete works are now at 63% completion, while piling, steel installation and backfilling continue to move forward alongside one another.
More than 260 engineers, technicians, contractors and workers are on site each day, contributing to the project as new materials arrive and different parts of the complex continue to develop.
While changes happen they become easier to see with every update. More buildings are taking shape, more structures are being completed and another important phase of the project is steadily coming together. Every stage completed is the result of the work taking place on site each day, bringing the TosyaliSulb steel complex one step closer to becoming a reality.